Construction delays for large building projects aren’t unusual. So, it wasn’t at all surprising last week when the city manager of St. Marys started explaining to members of the city council why the relocation of City Hall to a newly renovated building next month wouldn’t happen as planned.

What was unusual, however, is the reason the city manager, Mike Mahaney, gave for the delay: ICE.

Mike Mahaney

In the previous month, Mahaney said agents of U.S. Immigration and Customs Enforcement had “showed up” twice at the planned site of a new City Hall, the Express Scripts building in midtown St. Marys, without notifying either the local police department or sheriff’s office. The first time they took away 18 workers who were refurbishing the building, he said.

In response to the ICE sweep and with a December deadline for completing the city hall project looming, the contractor recruited replacement workers in Atlanta, paying them $13-an-hour more to pick up where their predecessors left off, according to Mahaney. Soon after, ICE agents had shown up at the work site again, taking away a dozen workers.

“You talk to some of the developers out here. You talk to some of the restaurants,” Mahaney told the council meeting, noting that the city hall project isn’t the only undertaking in the city of nearly 20,000 people trying to operate under the specter of ICE operations and the wildly unpredictable labor pool that has resulted.

But forget the deadline for the multimillion-dollar project, the clearly exasperated city manager said. “There’s no way we’re going to get into that building by December because we don’t have the workers.”

Withering criticism

Some attendees who listened to Mahaney at the Nov. 16 meeting were having none of it, regardless of the city manager’s evident frustration with the project’s lack of progress. Robert Moore was one of them.

During the public comment period, Moore ripped into Mahaney for appearing to use ICE operations as an excuse for not completing the city hall project on time.

“You made it sound like, ‘Oh God, we’re so behind because they whisked away 12 people.'” Although the immigration status of the workers at St. Marys site isn’t publicly known, He implored city officials to demand a refund from the contractor for “breaking the law” and “employing people that are illegal.”

Another attendee, Roger Shaw, was no less withering.

“To blame ICE for coming in and getting illegals is like stepping in dog crap and blaming the dog. You know this is illegal. The contractor knows it’s illegal,” Shaw said. He went on to describe to Mahaney and the council how “illegals” had driven him and his business out of southern California.

“You hire the Third World here, you become the Third World,” he said. “Whoever that contractor is [for the city hall project] should go to jail.”

Not all the public comments were scathing.

One St. Marys resident told the council he had drafted a lot of contracts in his professional life and always included language requiring that contractors use workers that are U.S. citizens or have green cards. Otherwise, he cautioned, they’d be penalized.

“We just need to tighten up on our contracts a little bit, guys,” the man advised.

The reported contractor for the St. Marys city hall project, Overholt Construction in Jesup, didn’t reply Monday to a request for comment on its hiring practices for the project.

Manager: Not in the city’s interest

During his remarks last week at the council meeting, Mahaney deplored ICE’s lack of notification to local law enforcement agencies before its two operations targeting the city hall renovation site.

In his 50 years in government, he said, federal law enforcement agencies such as the U.S. Marshall’s Service, the FBI, and Homeland Security always provided such notification because if they fail to, “that’s the way my officers get killed.”

But St. Marys and other communities across the U.S. are being encouraged by ICE to join them in carrying out immigration policy, most of which is now focused on targeting those suspected illegal immigrants for deportation, whether they are the “worst of the worst” or not.

The number of local and state law police officers working with ICE has doubled in the last eight months, according to a recent report from the immigration reform advocacy group FWD.us.

Much of flourishing cooperation falls under an ICE program called 287(g) that deputizes state and local police for immigration enforcement, including arresting suspected illegal immigrants. Under the partnership, local forces can receive funds and equipment.

Mahaney was urged by attendees at the meeting to enter the 287(g) program, partly, they said, to ensure local police officers and sheriffs would be notified about upcoming immigration enforcement operations and remain out of harm’s way.

The county manager said that he, on behalf of St. Marys, had been offered $100,000 to enter the program but had refused. Such an agreement wasn’t “in the interest” of the city, he said, giving no details.

ICE personnel can still come to St. Marys “because they have every right to deport people that are here illegally.”

Mahaney didn’t respond Monday to a request for further comment on last week’s council meeting and the proposed ICE partnership.

Craig Nelson is a former international correspondent for The Associated Press, the Sydney (Australia) Morning-Herald, Cox Newspapers and The Wall Street Journal. He also served as foreign editor for The...